A new mixed-use six-story building meets ambitious client goals in the heart of San Francisco’s Union Square.

  • Innovative Design

    Combining form and function in the unique oval columns required tight rebar coordination and special forms during construction.

  • Advanced Analytics

    To allow for the open glass facade, Tipping designed a hybrid structural approach that initially appeared counterintuitive but was validated through performance-based analyses.

  • Integrated Value

    To maximize interior volumes, Tipping designed post-tensioned slabs that minimize floor thickness. The design includes pre-planned stair openings to accommodate flexible future tenant layouts without re-routing the cables.

We harness our advanced analytics’ capabilities to predict structural behavior and gain key insights to develop optimized, data-driven design solutions—creating real value for clients and building owners.

Learn More

We’re hyper-focused on providing useful insights early in the design process to better inform key decisions, control cost, and minimize disruptive surprises. By internalizing project-level goals, we’re better able to help achieve them.

Learn More

As industry leaders, we collaborate and innovate to create low-embodied energy, sustainable design solutions that are efficient, cost-effective, and seek to reduce carbon output to minimize construction’s environmental impact.

Learn More

We combine innovative design and a collaborative and responsive workflow to deliver tailored, effective, and unexpected seismic design solutions that help protect our clients’ high value investments and facilitate post-earthquake operations.

Learn More

Instead of textbook solutions and conventional approaches, we ask deeper questions to unlock possibilities. Through ingenuity and a thoughtful application of engineering first-principles, we develop more responsive and efficient structural designs.

Learn More

At the bustling corner of Grant Avenue and Sutter Street, this new six-story retail and office building is the first ground-up development in San Francisco’s Union Square this century. With three lower floors of premier retail space and three levels of Class-A office above, open floor plates and no obstructions along the three street frontages were key for full retail access and visibility.

Innovative structural approach

Only steps away from the Dragon Gate in a neighborhood full of buildings with distinct personalities, 300 Grant needed a strong presence of its own. The client envisioned long, open spans that created a sense of transparency, welcoming tenants and shoppers alike. To facilitate this vision, the Tipping team devised an innovative asymmetric seismic system, requiring careful performance-based analysis. 

The client also had ambitious goals for future tenant flexibility, requiring an anticipatory design for potential configurations of the space. The Tipping team leveraged a response-spectrum analysis to establish the viability of our unconventional design, performing sophisticated shaking simulations using nonlinear response-history analyses.

  • Location

    San Francisco, CA

  • Square Footage

    71,000

  • Cost

    $33 million

  • Completion Date

    2020

  • Owner

    Lincoln Property Company & St. Bride's Managers LLC

  • Architect

    MBH Architects

  • Contractor

    Hathaway-Dinwiddie Construction Company

  • Photography

    Matthew Anderson, Tipping Staff

prj_300Grant_3041-edited

The double-oval reinforced-concrete columns at 300 Grant's corners add to the building's eye-catching geometry

prj_300Grant_3044

A terracotta and aluminum facade system, topped with a "halo," provide sunlight diffusion and a sense of privacy for the upper office floors

Construction sequencing for post-tensioned slab and column

Exterior columns as architecture and structure

The building’s corners present an opportunity to give 300 Grant’s functional structure a sense of intrinsic architectural design, with custom sculptural concrete columns comprised of two ovals.

Because the columns actively support the post-tensioned slabs, the process of affixing the tendons in the anchors while maintaining a smooth finished surface had to be carefully orchestrated. The edge of the slab pour was held back from the exterior face of the columns with form savers, and then the column’s vertical reinforcing was installed after tendon stressing occurred.

Analytical model

The slightly L-shaped building’s lateral system consists of a moment frame and two concrete shear walls. The shear walls take advantage of the location of the two blind walls that shape the L and cradle the adjacent building, aligning with 300 Grant’s center of mass. The concrete moment frame, located one bay inset from the Grant Street facade, provides torsional resistance.

Our analyses demonstrated that the hybrid moment-frame-and-shear-wall lateral system would perform well when subjected to seismic shaking, exhibiting uniform deformation despite the irregular configuration of walls and the frame. Performance-based analysis was used to proportion the structural members and tune the structure’s deformation and minimize its torsional response.

Three "blockouts" in the post-tensioned slabs simplify future modifications

Flexibility for future tenants

To accommodate the potential needs of future tenants occupying varying configurations of the office and retail floors, Tipping designed “block outs” at three central locations within the post-tensioned slabs to facilitate the future installation of internal stairs. Mild-steel block outs were used, and tendons were carefully wrapped around them to ensure that the code requirement for distributed tendons is maintained. This proactive measure will simplify the process of adding vertical circulation without the typical challenges associated with modifying existing post-tensioned slabs.

prj_300Grant_4296

The columns required careful sequencing coordination with the general contractor

prj_300Grant_4295_recolored-annotated4

The concrete floor slabs were post-tensioned before the columns could be installed and poured